Description: Eight miles, extending north from 75th Avenue South to South Dearborn Street.
Start Date: April 2006
End Date: December 2008
Collision Results (Results compare collision data from the three years before the project started to the two years after the project ended):
Total = down 1% (569 to 565), 1706 versus 1129
Injury = down 8% (349 to 322), 1046 versus 643
Alcohol-Related = up 16% (22 to 26), 66 versus 51
Fatal and Serious = up 26% (13 to 16), 38 versus 32
View Final Results (pdf)
Start Date: April 2006
End Date: December 2008
Collision Results (Results compare collision data from the three years before the project started to the two years after the project ended):
Total = down 1% (569 to 565), 1706 versus 1129
Injury = down 8% (349 to 322), 1046 versus 643
Alcohol-Related = up 16% (22 to 26), 66 versus 51
Fatal and Serious = up 26% (13 to 16), 38 versus 32
View Final Results (pdf)